Demolition and reconconstruction

The demolition started on 22nd January and only took a few days before all the structure had gone.














Groundworks:  hammering was felt to be too disruptive locally so pile were bored and back filled with concrete.
The small yellow dots in the ground show the pile position sites.




The piles are visible in the foundation trenches - which are very wet at 1.5m as predicted.


Superstructure in early March


Base in Mid March, drains and footings all signed off.


By later in March....


Rooms start to appear

and external walls




At the end of April the roof trusses went up. Once the skin and rood of the building are complete then the fitting out with electricals and services starts.



Soon the roof was watertight leading to the first fix phase.